A strong cost and sustainability argument is made for the use
and implementation of polished concrete floor systems. This article highlights and defined the real,
actual cost savings associated with the use of a polished concrete solution
versus other popular solutions.
WESTLAKE, Ohio -- School officials say that spidery cracks
in the polished concrete floors of the new Westlake High School are not an
indication that those floors are failing.
The $50-million, 265,000-square-foot school opened in
September to glowing reviews from many, but some residents have since raised
questions about the cracks in the floor and about why there weren't enough
lockers for students when classes started.
Superintendent Dan Keenan said the cracks -- none of which
is large enough to get a fingernail in, he said -- are the result of the
natural drying process of concrete. He described it as an aesthetic issue only.
"Our floors are solid," Keenan said.
He said he recognizes that there are residents, including some
students, who don't like the look of the concrete. But Keenan said the district
chose that option because it's much cheaper than terrazzo and can be cleaned
with only hot water and soap, rather than requiring regular stripping, waxing
and buffing.
By choosing the concrete floors, the district saved about $1.8 million
between the high school and the new Lee Burneson Middle School, which also has
concrete floors, Keenan said. Those savings, which don't count the reduced
maintenance costs, were redirected to classroom space, he said.
The superintendent said the district got input from
residents before deciding on what to include in the building projects after
voters approved an $84-million bond issue in 2010 for capital improvements. Tile
floors would have been an even cheaper option, Keenan said, but the decision
was made to install a so-called "lifetime" floor such as concrete or
terrazzo.
He said the district decided to opt for a
"well-equipped Chevy over a Cadillac." Keenan said that at the high
school, where 63,690 square feet of the floors are concrete, the savings
compared to terrazzo amounted to about $1.3 million.
Dave Puffer, supervisor of construction projects for the
district, said the cracks are only on the surface of the floor. He said an
additive was used in the concrete to provide a vapor barrier that prevents
moisture from coming up from the ground. Like Keenan, Puffer said the cracking
does not affect the integrity or functionality of the floors.
Keenan said the cracks are not in all areas, but some may
extend 10 feet down a hallway, following a drying pattern.
As for the locker issue, Westlake High School Principal Tim
Freeman said classes began with 110 fewer lockers than officials had asked for
on construction drawings. Freeman said he discovered the shortage when he was
able to get into the building, which was still under construction, in August. A
new order was placed with the manufacturer by Aug. 28, at no additional cost to
the district, to get the rest of the lockers that should have been shipped
initially, Freeman said.
He said no lockers were assigned on the first day of school
and that after that the available lockers were assigned first to freshmen and
sophomores under the reasoning that underclassmen needed them most, then to
juniors and finally to seniors. Freeman said about 51 seniors whose names fall
at the end of the alphabet were left without lockers, but were given the option
of using athletic lockers.
He said the ordered lockers arrived and were installed after
about nine weeks so that as of this month all students have lockers.
Keenan emphasized that the number of lockers was correct on
the drawings and that the error was in what was actually shipped. "It was
unfortunate and inconvenient. Our kids didn't deserve that," the
superintendent said. "I wish it could have been avoided."
There are still some projects to be wrapped up at the high
school. Keenan said that, as planned, construction continues on the music wing
at the high school, grass and landscaping will be done in the spring and other
punch list items are being completed.
Source: Cleveland.com
No comments:
Post a Comment