Construction on the stalled National Museum of Industrial
History in South Side Bethlehem could finally start again.
The organization submitted an application to the city for
a building permit and its construction manager, Alvin H. Butz Inc. of Allentown
will begin seeking bids for the third phase of construction, which encompasses
the museum’s concrete slab and underground utilities.
“We are going out for bids this week, that process will
take at least a month,” said Charles Marcon, museum board chairman and
president, this morning. “I’m hoping by the middle of November, there will be
activity at the site.”
The museum plans to display industrial era artifacts from
the city.
Last October at Bethlehem Steel’s former research lab at
Lehigh University’s Mountaintop Campus in Bethlehem, trucks loaded large steel
testing and manufacturing equipment from one of the buildings and transported
the pieces to the museum.
At the time, a new construction phase appeared imminent.
Steve Donches, then CEO and president of the museum, said the building was
under construction, with the exterior restored and the museum ready to bring
the exhibits in.
Now, once this stage is complete, the museum, which owns
the property, will move on to interior construction of the building and exhibit
installation in preparation for opening its doors to the public in early 2016,
Marcon said.
Earlier this year, a Northampton County grand jury report
called for the Pennsylvania state attorney general to investigate the museum
board’s handling of the finances for the museum project.
“We still have the specter of the investigation over our
heads,” Marcon said.
Marcon said the board is still awaiting the verdict from
the attorney general.
“It’s been two and a half years that we’ve been in
limbo,” Marcon said. “We’ve been kind of heading down this road for some time
now.”
Every museum depends on donations to keep the doors open,
he added.
However, an anonymous $3 million donation that the museum
received in June is spurring the start of construction, Marcon said.
At this point, the museum wants to start the construction
of the museum’s concrete slab and underground utilities but will wait until the
attorney general’s verdict is received before moving forward with more
construction, Marcon said.
This way, if the attorney general decides to shut the
museum down, the organization can still sell the building, Marcon said.
“Anything that we can do to enhance the quality of life
in the Lehigh Valley is worthy of pursuit,” Marcon said. “There is an enormous
amount of interest, not only locally, but nationally. This is an enhancement of
the whole Bethworks site.”
Architectural plans for the two-story museum are complete
and have been supplied as part of the permit application process.
David Scott Parker Architects LLC, of Southport, Conn.,
working with area engineering firms, developed the design and construction documents.
Parker has worked on several projects in Historic
Bethlehem, including the Burnside Plantation, Moravian Smithy and Moravian Bell
House, according to a news release.
Previous construction phases included a new roof and
exterior restoration, and the installation of more than 200 windows.
The combined value of those two phases was about $2.5
million.
The fourth phase of construction will complete interior
construction of the building, and the fifth and final phase will include
installation of exhibits and the entrance plaza.
Marcon said the total construction project is valued at
$6 million.
“We still have an ambitious vision,” Marcon said. “It’s
more than a Bethlehem Steel museum, our goal is to be national.”
For the first part of the project, the exhibits will
highlight textiles, steel and energy, but the museum would like to eventually
add other industries, Marcon said.
The museum is located on East Second Street as part of
the BethWorks project.
Source: LVB.com
No comments:
Post a Comment