A modular building project in the Bronx is moving along,
with four of its 64 total modules added each day.
|
Modular-building boosters, including traditional owners,
developers, contractors and designers, maintain that off-site construction is
faster, safer, leaner, greener, better quality and potentially less costly than
site construction. But there is a big hitch, they caution: Building teams are
not likely to reach modular delivery's pot of gold unless they plan and execute
the off-site strategy properly. And that is no simple proposition.
"Everyone thinks it's a silver bullet," says
Jeffrey M. Brown, the developer and general contractor for the Stack, a mostly
factory-built seven-story residential building in Upper Manhattan that opened
in May. "It really isn't unless you put the right ingredients in the bowl."
Few know that better than developer Forest City Ratner
Cos. (FCRC) and its team building the world's future tallest modular tower: the
32-story B2 BKLYN residential building in Brooklyn, N.Y. Stalled at 10 stories,
the B2 project at the $4.9-billion Pacific Park Brooklyn site, until recently
called Atlantic Yards, is a glaring example of modular gone sour. The B2
project, designed by SHoP Architects, was going to take factory-built modular
to the next level through the use of sophisticated digital tools to design,
fabricate and manage assembly of the 930 modules.
Instead of a poster child for improved high-rise modular,
B2 has become the poster child for modular run amok. Unable to solve their
differences privately over delays and cost overruns, FCRC and Skanska USA Building
Inc.—B2's construction manager and FCRC's partner in a new modular plant,
called FC+Skanska Modular—are battling it out in court.
Despite the situation, both Skanska and FCRC say they are
committed to factory-built modular. "We believe in modular as the future
of the industry," says Richard A. Kennedy, Skanska's co-chief operating
officer.
In a Sept. 4 letter to Kennedy, FCRC President and CEO
MaryAnne Gilmartin says, "We remain resolute in modular technology's
potential and promise."
Modular-building veterans are rattled by the B2 feud.
"I'm angry because it gave this industry a black eye," says Tom
O'Hara, vice president for business development at Capsys Corp. The factory
builder is supplying modules for a 65-unit residential building in the Bronx,
N.Y., called 3361 Third Avenue.
Modular is of interest to traditional builders because,
in part, it has been identified as a means for improving building production.
Collaborative delivery and advances in digital tools for design, coordination,
clash detection, project management and fabrication support the movement, as do
advances in lifting equipment.
"This is not a new process, but there is newfound
interest of late," says Tom Hardiman, executive director of the Modular
Building Institute (MBI).
Until 2009, the 31-year-old MBI had no traditional
contractor members. Now, there are a dozen, including Gilbane Building Co.,
Mortenson Construction and PCL, but not Skanska or FCRC.
Off-site construction is most apppropriate for buildings
with repetition, including schools, housing, hospitals, multifamily
residential, hotels and dormitories. Many recent modular buildings are a mix of
site-built, non-repetitive lower floors topped by assemblies.
The B2 drama is serving as a cautionary tale. The
85-member Off-Site Construction Council, formed last year by the National
Institute of Building Sciences (NIBS) to advance all types of prefabrication
and preassembly, "is interested in learning what works and what does not
in all projects that pursue the use of off-site construction," says Ryan
Colker, the council's director. "As the case unfolds, we will be looking
to understand any role off-site construction had in the dispute."
To the NIBS council, "off-site construction" is
the design, fabrication and assembly of building elements at a location other
than their installed location. "Off-site construction is characterized by
an integrated planning and supply-chain optimization strategy," says the
council, in its draft off-site construction glossary.
Permanent modular construction, also known as volumetric
or 3D modular, is a subset of off-site. NIBS defines it as "an innovative,
sustainable construction delivery method utilizing off-site, lean manufacturing
techniques to prefabricate single or multistory whole building solutions in
deliverable module sections." PMC buildings are made in a safe, controlled
setting and can be framed in wood, steel or concrete. Modules can be delivered
with mechanical-electrical-plumbing systems, fixtures and interior finishes.
"The application of manufacturing principles to
design and construction enables us to put buildings together in more innovative
ways," says Sue Klawans, Gilbane's director of operational excellence and
planning and the council's vice chair. "Why bring 2 million individual
bricks, studs and wire connectors to the site? Let's reduce that by a factor of
10 or 100."
Off-site construction leaves "many owners,
architects and builders confused and sometimes put off by the process,"
says Ryan E. Smith, chairman of the NIBS council and director of the Integrated
Technology in Architecture Center at the University of Utah. "It is not
easy for those in their first rodeo."
"Not easy" is an understatement for the first
residential rodeo of FCRC and Skanska. Sited up against the two-year-old
Barclays Center arena, B2 is already more than a year behind its original
December completion date. On Aug. 27, Skanska stopped work at both the site and
the FC+Skanska Modular plant, furloughing more than 150 workers and raising the
ire of Forest City. Lawsuits have followed.
Skanska is asking for more than $50 million in damages
over its $117-million fixed-price contract to cover alleged "commercial
and design issues." Forest City, on a campaign to reopen the plant,
alleges Skanska has breached its contract after "multiple failures and
missteps" that led to "massive delays and cost overruns."
John Erb, vice president of sales and marketing for
Deluxe Building Systems Inc., says, "If a project goes awry, it means the
team didn't know the process. It's like me trying to perform open-heart surgery
tomorrow without any training." Deluxe supplied modules for the
90.5-ft-tall Stack, the U.S. record-holder for the tallest completed modular
building.
Factory modular is "a science" and
"outsiders" should not venture into the business, which is
drastically different from traditional site construction, says Capsys' O'Hara.
There are flaws in the B2 scheme, say those experienced
with modular, especially the "still" construction plan developed by
XSite Modular—Forest City's modular-business partner-consultant before Skanska.
Unlike an assembly line, still construction is built in place by teams, each
assigned to a vertical line of identical units. The approach and the 913 unique
modules do not take advantage of the efficiencies of assembly-line production,
say modular experts.
O'Hara also maintains that the B2 modules, which include
facade panels, are too complete. Most modules don't include the panels because
they often cause alignment problems during field fit-up.
FCRC and Skanska declined to comment on the criticism of
their approach.
Modular delivery disrupts the economics, workflow,
contracts, coordination points, insurance and building regulations of
conventional site-built projects. There can be issues with the union building
trades. Off-site delivery raises questions even about warranties versus
bonding. Is a bathroom pod a product or not?
Plan review also must be completed early, but most
buildings departments are not geared up for this.
Transportation, picking, setting, tolerances, on-site
stitching and detailing are different from site construction. "I have
tremendous respect for logistics, which can make or break a project," says
the Stack's Brown. "Transportation is a big piece of the cost."
Global Building Modules—with FXFowle Architects as
architect, LERA as structural engineer and Dagher Engineering as mechanical
engineer—is trying to market a patented modular system that would solve some of
the transportation issues. The concept calls for steel-framed modules that are
dimensionally the same as shipping containers; the modules could be produced in
port areas of cheap labor and shipped by sea and rail to sites.
So far, there have been no takers. "Everyone is
always blown away by how technically resolved the idea is, but each asks, 'Who
has done a building?' " says David Wallance, a senior associate at
FXFowle.
Project Frog has demonstrated a way around flat-bed-truck
limitations for 3D modules. The company supplies kits of parts to the site;
only bathroom pods are 3D. "Flat-pack construction is affordable to
ship," says Ann Hand, Project Frog's president and CEO.
Modular delivery relies on owner buy-in and early team
collaboration. With 3D modular, there is no fast-tracking, but there is
resequencing. Design decisions have to be finalized up front, to allow
prospective modular builders to price the job and the winner to order supplies.
"Bathroom finish colors and tile patterns are not
typically set during the foundation-document phase," says Maja Rosenquist,
project director with Mortenson Construction for the $623-million Exempla Saint
Joseph Hospital, which has off-site-built elements and is nearing completion in
Denver.
The early decisions for the Bronx project "put
enormous pressure on us," says James McCullar. His eponymous firm is the
architect for the 64-module project.
It's best to test the waters of modular in stages.
Gilbane started with preassembled multitrade utility racks on a U.S. project.
Then, it added vertical risers to the next job: the 270,000-sq-ft Global
Technical & Innovation Center in Kerry, Ireland. The various prefabricated
components sliced three months off the laboratory's schedule, says Gilbane.
"The modular nature, developed in the [building information model],
allowed us to run a number of layout and cost scenarios early," says Ian
Howard, project manager for the client, the Kerry Group. "That gives us a
high degree of confidence."
Discounting glitches with the buildings department that
caused a three-month delay, the Stack would have taken two-thirds the time of
site construction, says Peter Gluck, of Gluck+, the Stack's architect
design-builder.
Mortenson commissioned the University of Colorado,
Boulder, to do a study on its 831,000-sq-ft Denver project to compare it to
site construction. The study concluded that the prefab approach for utility
racks, bathroom pods, exterior panels and head walls reduced the schedule by 72
work days. The job used 29,500 fewer hours of labor, resulting in $2.6 million
in productivity savings, and diverted 150,000 hours of labor off-site. There
was $4.3 million in indirect cost savings, but direct costs were 6% more than
site construction, according to the study.
"Certain elements were more expensive until the
indirect costs were accounted for," thanks to the fear factor in the
pricing, says Bill Gregor, Mortenson's construction executive for the hospital.
Mortenson holds a prefab charrette to determine the
off-site path for a project. Another important step is a full-scale prototype
to avoid repeating a mistake hundreds of times.
Some say design-build is the best delivery system for
modular, but any collaborative approach will work. Architect James B. Guthrie,
president of Miletus Group Inc., a modular design-build firm, has doubts about
modular becoming mainstream any time soon. Until there is a better knowledge
base and a better supply chain, "modular won't become widespread," he
says.
The NIBS council was formed to fill the knowledge gap and
gather metrics to prove the case, especially to reluctant owners. "We've
recognized it's a challenge to capture some of the potential
efficiencies," says Colker.
To help foster off-site, the council recently posted two
online surveys. The deadline for responses is Oct. 15.
The industry survey, available online here, is intended to
identify the opportunities and challenges associated with the use of off-site
construction processes and technologies.
The academic survey, available online here, will determine
the scope of off-site construction teaching and research in U.S. colleges and
universities. Results will be used to support the development of tools and
resources for the schools.
The council also is seeking $150,000 for an off-site
construction implementation guide, to help demystify the process.
Demystification is already under way in the U.K., home to
the world's tallest completed modular tower: a 24-story dorm at the University of
Wolverhampton. The 10-year-old industry group Buildoffsite has published
hundreds of case studies that detail the benefits of off-site solutions. They
are available at www.buildoffsite.com.
Pitfalls aside, mainstream builders' move toward modular
delivery is a logical step in one of biggest transformations in the
construction industry since the introduction of the combustion engine and
electric power, says Gilbane's Klawans.
"We're in the midst of creative destruction and
reinvention of our industry," says Klawans. "It's exciting."
Source: ENR