Wednesday, September 3, 2014

Conshohocken borough building bid comes in $900,000 below estimate - Regional Contractor, T.N. Ward, Submits Low Bid


GMCS Editorial:  Congratulations to David Panichi and the entire T.N. Ward construction team for their low bid on this project.

CONSHOHOCKEN — A Lower Merion general contractor and construction management firm was the apparent low bidder Friday to build the Conshohocken borough hall, police station and retail spaces in the former Verizon building on Fayette Street.

TN Ward Company submitted the $10,497,600 electronic bid to www.PennBid.net and it was opened by Borough Engineer Paul Hughes along with two other base bids at the borough engineer’s office. Allied Construction Services of Philadelphia bid $10,583,439 and Murphy Quigley Co. Inc. of Lower Merion bid $12,976,000.


“There are nine alternate bid options in the bid package but the base bid drives everything,” said Hughes. “We will examine the bids to make sure TN Ward was a ‘responsive bidder,’ which means they included all the required construction elements in the base bid.”

Hughes will prepare a report on the bids and deliver them to the 7 p.m., Sept. 3, workshop meeting of Conshohocken council where the bids will be discussed in detail. Members of council were vocally concerned about an $11,406,395 project cost estimate for the project delivered to council in mid-July by the developer, Keystone Property Group (KPG) of Lower Merion. The $11.4 million estimate was $949,096 above an earlier cost tally.

Council members asked Hughes to include the nine alternate options in the bid package to give council economic manuevering room to slice elements out of the project costs.

The TN Ward alternate bid package included $713,000 for the second entrance on Fourth Avenue, including sitework, structures, stairs, exterior envelope, interior re-configuration and all associated mechanical, electrical, plumbing and fire protection elements.

A vegetative tray system on the main roof would cost $103,500. A roof screen for the rooftop mechanical systems would cost $46,500. A six-panel, closed-loop solar hot water array would cost $38,500. An upgrade in the rubber roof thickness, from 0.060 inch to 0.090 inch, would cost $13,500.

TN Ward officials said substituting a decorated pattern for a plain pattern on the parking lot retaining wall would add $22,000 to project costs if it is adopted by council.

Dennis Furness Jr., a project manager for TN Ward Company, was the only bid representative at the bid opening. Once the bids are opened electronically by Hughes, they are available for viewing online by the other bidders, Ward said.

“It is always nice to get more work,” Furness said. “Of course, you don’t have it until you actually sign a contract.”

Earlier in the week, Borough Manager Richard Manfredi said council could award the construction bid at the Sept. 17 meeting, “but that is a very aggressive schedule.”

He said it was more likely that council would either schedule a special meeting for late September or take official action at the Oct. 15 meeting.

Hughes said that demolition work at the Verizon building at Fourth Avenue was “substantially complete” on Friday making it ready for the construction phase.

Council has scheduled approval for a $13 million borrowing for the Sept. 17 meeting to finance construction, equipment and furnishings for the new borough building.

Source: Times Herald

No comments:

Post a Comment