For its Waterford, Conn., Cancer Center, a comprehensive
treatment facility affiliated with Dana-Farber Community Cancer Care, Lawrence
+ Memorial Hospital decided to try something new: true three-party Integrated
Project Delivery.
The contractual agreement covered L+M, architecture/engineering
firm TRO JB, and construction manager Suffolk Construction, with programming,
design, and construction all informed by Lean principles.
To further extend the collaborative theme, this three-party
project management team invited three trade partners to participate in an
incentive compensation layer, involving a pool consisting of at-risk potential
profits.
TRO JB, Suffolk, and three handpicked HVAC/plumbing,
electrical, and site work subs would participate in the ICL. If the project
came in over budget or exceeded the schedule, the ICL profit pool would be
tapped to pay the penalties. If the facility came in under budget or ahead of
schedule, the ICL group would get the profit pool plus 50% of the savings, with
the hospital pocketing the remaining savings.
Project Summary:
Lawrence +
Memorial Hospital Cancer Center
Waterford, Conn.
BUILDING TEAM
Submitting firm:
Suffolk Construction (GC/CM)
Owner/developer:
Lawrence + Memorial Hospital
Architect, MEP/FP:
TRO JB
Structural:
Simpson Gumpertz & Heger
Civil:
DiCesare-Bentley Engineers
GENERAL
INFORMATION
Project size:
47,000 sf
Construction cost:
$24 million (IPD contract value $34.5 million)
Construction
period: May 2012 to September 2013
Delivery method:
Tri-party integrated project delivery
Early collaboration on the design, schedule, budget, and
quality goals was a must for making the plan work. Using 3P (Production
Preparation Process) Lean design and pull planning tools, the Building Team was
able to make key decisions efficiently. Input from about 70 Cancer Center
stakeholders—including administration, medical staff, support staff, patient
advocates, and partners from Dana-Farber—was solicited in an intense three-day
3P charrette, which resulted in schematic draft floor plans.
Only minor changes were needed after this point, testifying
to the effectiveness of the event. (The most significant contract alteration,
requested by L+M as a value-added item, was a geothermal well field system that
will pay for itself in just a few years.)
A co-location center set up in two of L+M’s hospital
conference rooms was made available to the Building Team for the duration of
the project. This home base proved crucial to ensuring efficient communication
and also provided a convenient setting for stakeholder evaluation of mockups.
As a result of the collaborative efforts, the overall
project schedule was reduced by six months, and the facility came in $1.2
million under budget. Actual construction was completed in only 10 months,
meeting a “stretch goal” previously set by the client. Streamlined front-end
decisions played an important role, including an RFI process that was 80%
shorter than the client had previously experienced.
Building Team Awards judges were impressed with the
participants’ ability to weigh wants and needs and craft a facility that
achieved ambitious goals. The client has engaged Suffolk and TRO JB for a
second IPD contract, this time to renovate a three-story medical office
building. As with healthcare itself, new ideas about delivery are proving
indispensable to positive outcomes.
Source: BDC
Network
No comments:
Post a Comment