Curtain wall façade brings new levels of natural light to
patient rooms in an unusual vertical addition.
The University of Virginia Medical Center in Charlottesville
took a novel approach when expanding an existing patient tower. Rather than
adding a wing, the Building Team attached an eight-story, 127,000-sf expansion
to the front façade.
SmithGroupJJR designed the 34-foot-deep addition, which
comprises stacked 12-bed nursing units and a new mechanical penthouse. Existing
columns and beams were upgraded to address new seismic requirements, and new
elevators and structural reinforcements were added to allow penetrations of the
original building. A 45-foot helipad was constructed above the existing roof,
with two high-speed elevators for quick access.
The light-filled rooms, providing 72 acuity-adaptable
patient beds, feature soft, neutral colors and are flexible enough to support
all phases of the treatment process. The building can now serve a wide range of
critical-care departments, including pediatric, postpartum, surgical stepdown,
and ICUs for the neurology, thoracic cardiology, and general medical patient
population.
The construction team, led by GC/CM Gilbane, scheduled the
work to minimize impact on patients and medical staff during construction.
Prefabricated steel and curtain wall systems were installed on evenings and
weekends, when passersby were less frequent. Seismic and structural work was
scheduled at the same time as related lower-level renovations.
Project summary
University of
Virginia Medical Center Patient Tower Expansion
Charlottesville,
Va.
BUILDING TEAM
Submitting firm:
SmithGroupJJR (architect)
Owner/developer:
University of Virginia Facilities, Planning and Construction Department
Structural:
Spiegel Zamecnik & Shah
MEP: AKF Engineers
GC/CM: Gilbane
GENERAL
INFORMATION
Project size:
127,000 sf
Construction cost:
$69 million
Construction
period: August 2008 to February 2013
Delivery method:
CM as agency
A 2-foot, 8-inch gap between the new construction and
existing building was important for allowing the hospital to remain open with
minimal distractions. The noise-buffering gap was not infilled until the
addition was fully enclosed, followed by removal of the existing façade and
renovation of the adjacent space. A heavy use of BIM helped optimize
efficiency.
Judges were impressed with the coordination required. “I can
only imagine the challenges associated with isolating existing utilities and
systems in prep for the removal of the façade, the temporary structures/systems
required to keep the weather out while they made the tie-in to the existing
structure, as well as dealing with vibration, noise, and dust on all eight
floors all at the same time,” says juror Drew Martin, Senior Project Manager
with Clark Construction.
“The infrastructure alone is a huge challenge on a project
like this,” says Nathaniel Snydacker, PE, LEED AP, Vice President at
Environmental Systems Design. “Extending existing services and seamlessly
integrating new equipment to support the additional area and associated loads
requires precise coordination between the engineers, architects, and contractors.”
“This project
exemplifies the meaning of teamwork and cooperation,” concludes Terry Fielden,
LEED AP BD+C, Director of K-12 Education for International Contractors. “The
incorporation of this ‘laminated’ addition into a fully functioning hospital
demanded daily routine adjustments and constant cooperative collaboration from
all hospital staff. The end reward is nurturing patient care.”
Source: BDC
Network
No comments:
Post a Comment